1 | DAP | Z06-5315 | 18/01/2008 | Granted | 18/01/2008 | V | |
2 | SRV | Z08-3745 | 14/04/2008 | Approved | 30/04/2008 | V | Increase in security after lodgment of MOP for 2008 to 2011 |
3 | TRF | Z08-2964 | 03/04/2008 | Registered | 08/07/2008 | V | |
4 | RSC | Z08-3745 | 28/05/2008 | Approved | 28/05/2008 | V | Increase in security after lodgment of MOP for 2008 to 2011 |
5 | DSC | Z08-3745 | 05/06/2008 | Approved | 05/06/2008 | V | New security lodged for MOP 2008-2011 |
6 | AGR | Z08-2964 | 03/04/2008 | Registered | 22/07/2008 | V | Narrabri Deed of Cross Charge |
7 | AGR | Z08-2964 | 04/07/2008 | Registered | 25/08/2008 | V | Deed of variation |
8 | AGR | Z08-2964 | 04/07/2008 | Registered | 25/08/2008 | V | Deed of Novation |
9 | AGR | Z09-1110 | 03/02/2009 | Registered | 10/02/2009 | V | Deed of Covenant - Royalty Deed - Add EDF Trading |
10 | TRF | Z09-1110 | 03/02/2009 | Registered | 20/03/2009 | V | Addition of EDF Trading Australia P/L as Holder |
11 | AGR | Z09-1110 | 03/02/2009 | Registered | 10/02/2009 | V | Deed of Covenant - Royalty Deed - Add J-Power Australia |
12 | TRF | Z09-1110 | 20/03/2009 | Registered | 20/03/2009 | V | Addition of J-Power Australia Pty Ltd as Holder |
13 | TRF | Z10-0256 | 07/12/2009 | Registered | 18/01/2010 | V | Addition of Daewoo International & KORES Narrabri as Holders |
14 | AGR | Z10-0256 | 07/12/2009 | Registered | 20/01/2010 | V | Deed of Covenant-Royalty Deed - Add Daewoo & Kores |
15 | SRV | Z08-3745 | 20/07/2010 | Approved | 22/07/2010 | V | Increase in Security Following MOP Amendment |
16 | RSC | Z08-3745 | 27/08/2010 | Approved | 27/08/2010 | V | Receipt of Security following MOP Amendment |
18 | MSC | Z10-5918 | 04/09/2010 | Approved | 12/10/2010 | V | Letter of 27/8/10 re MAA changes was returned to sender. |
19 | DSC | Z08-3745 | 28/10/2010 | Approved | 28/10/2010 | V | Refund of Cash Security |
21 | SRV | Z08-3745 | 24/08/2011 | Approved | 11/07/2012 | V | Increase in security following submision of MOP |
22 | RSC | Z08-3745 | 11/07/2012 | Approved | 11/07/2012 | V | Receipt of increased security following RCE |
23 | DSC | Z08-3745 | 11/07/2012 | Approved | 11/07/2012 | V | |
24 | RSC | Z08-3745 | 11/07/2012 | Approved | 11/07/2012 | V | Change of Banking Authority |
25 | DSC | Z08-3745 | 11/07/2012 | Approved | 11/07/2012 | V | Return of security following change of Banking Authority |
26 | AGR | Z10-0256 | 07/03/2013 | Registered | 20/03/2013 | V | Narrabri Deed of Cross Charge |
28 | SUS | Z14-1985 | 01/07/2014 | Approved | 01/07/2014 | V | Amendment of SMP Condition |
29 | EAA | MCV14/1095 | 08/09/2014 | Approved | 24/11/2014 | V | REF - 2D Seismic Survey, Drill Sites and Access Tracks |
30 | EAA | MCV15/22 | 12/01/2015 | Approved | 21/01/2015 | V | Variation to REF - Additional 2D Seismic Survey Line |
34 | EAA | MCV14/554 | 02/06/2015 | Approved | 15/06/2015 | V | SDN- Narrabri Mine- SE Longwall Panels Exploration Programme |
35 | SRV | Z08-3745 | 14/03/2016 | Approved | 16/03/2016 | V | Increase security required |
36 | RSC | Z08-3745 | 31/08/2016 | Approved | 31/08/2016 | V | Top up of security required |
37 | RSC | M08-3745 | 24/10/2016 | Approved | 24/10/2016 | V | Receive Security Certificate |
38 | DSC | M08-3745 | 24/10/2016 | Approved | 24/10/2016 | V | Disposal of Security |
39 | SRV | M08-3745 | 31/08/2016 | Approved | 29/06/2017 | V | Security Review - awaiting Minister's review |
40 | SRV | M08-3745 | 07/12/2017 | Approved | 12/01/2018 | V | Increase in required security |
41 | RSC | Z08-3745 | 19/01/2017 | Approved | 19/01/2017 | V | Change of security provider |
42 | DSC | Z08-3745 | 19/01/2018 | Approved | 19/01/2018 | V | Disposal of Security |
43 | RSC | Z08-3745 | 21/02/2018 | Approved | 21/02/2018 | V | Receipt of security certificate |
44 | RSC | Z08-3745 | 26/02/2018 | Approved | 26/02/2018 | V | Receipt of security certificate |
45 | APV | M06-5315 | 03/09/2018 | Approved | 03/09/2018 | V | Remove Labour & Expenditure/working requirement condition |
46 | VLE | M2006/5315/DOI | 09/01/2020 | Approved | 09/01/2020 | V | Remove Labour & Expenditure/working requirement condition |
47 | SRV | EF20/18449 | 04/03/2020 | Approved | 02/04/2020 | V | Increase in required security to $25,063,000 |
48 | RSC | EF20/18449 | 26/05/2020 | Approved | 26/05/2020 | V | |
49 | DSC | SF20/22743 | 28/05/2020 | Approved | 28/05/2020 | V | |
50 | RSC | EF20/18449 | 01/06/2020 | Approved | 01/06/2020 | V | |
51 | CHN | TMS | 28/07/2020 | Approved | 28/07/2020 | V | Change of Name - Daewoo International to Posco International |
52 | CHN | TMS | 06/08/2020 | Approved | 06/08/2020 | V | NAME CHANGED from ASIC search 6/8/20 |
53 | SRV | SF21/30320 | 18/03/2021 | Approved | 15/04/2021 | V | SRV Increase Rehabilitiation Cost Estimate |
54 | RSC | SF21/30320 | 31/05/2021 | Approved | 31/05/2021 | V | |
55 | RSC | SF21/30320 | 15/06/2021 | Approved | 15/06/2021 | V | Security received |
56 | DSC | SF21/30320 | 16/06/2021 | Approved | 16/06/2021 | V | |
57 | AGR | AGR-2021-62 | 29/10/2021 | Registered | 09/11/2021 | V | TMS |
58 | SRV | SF21/156968 | 13/12/2021 | Approved | 10/01/2022 | V | SRV Increase to Secure Funding for Rehab Obligations |
59 | RSC | SF21/156968 | 24/01/2022 | Approved | 24/01/2022 | V | RSC due to SRV Increase |
60 | DSC | SF21/156968 | 24/01/2022 | Approved | 24/01/2022 | V | DSC due to SRV Increase - Replacement withHigher Value Cert |
61 | DSC | SF21/156968 | 26/01/2022 | Approved | 26/01/2022 | V | DSC to return certificates |
62 | AGR | AGR-2022-4 | 02/02/2022 | Registered | 04/03/2022 | V | TMS |
63 | RSC | SF21/156968 | 09/02/2022 | Approved | 09/02/2022 | V | RSC due to SRV increase |
64 | DSC | MEG/SF21/156968 | 22/02/2022 | Approved | 22/02/2022 | V | DSC to complete SRV after Larger Value Cert was provided |
65 | RSC | MEG/EF21/14462#5 | 28/03/2022 | Approved | 28/03/2022 | V | Security Swap |
66 | DSC | MEG/EF21/14462#5 | 05/04/2022 | Approved | 05/04/2022 | V | DSC to Complete Swap |
67 | APV | VAU-2022-107 | 07/06/2022 | Approved | 19/08/2022 | V | Variation - Streamlining Mining Lease Conditions Project |
68 | TRF | TRF-2022-42 | 10/03/2023 | Registered | 15/03/2023 | V | TMS |
69 | AGR | AGR-2022-48 | 19/10/2022 | Registered | 28/10/2022 | V | Narrabri Deed of Cross Charge (Fifth) |
71 | SRV | MEG/15/838#3 | 01/06/2023 | Approved | 20/06/2023 | V | SRV to Secure Funding for Rehab Obligations - No Change |
72 | RSC | MEG/EF21/14462#14 | 15/08/2023 | Approved | 15/08/2023 | V | RSC due to Security Swap |
73 | DSC | MEG/EF21/14462#14 | 17/08/2023 | Approved | 17/08/2023 | V | DSC to Complete Security Swap |
74 | SRV | MEG/15/838#4 | 19/05/2024 | Approved | 14/06/2024 | V | SRV to secure funding for rehab obligations - No Change |
75 | AGR | AGR-2024-35 | 18/06/2024 | Registered | 03/07/2024 | V | TMS |
76 | DSC | TOM0000672 | 17/03/2025 | Approved | 20/03/2025 | V | Joint Security Group Management |
77 | SRV | SEC0001630 | 17/03/2025 | Approved | 20/03/2025 | V | Joint Security Group Management |