1 | DAP | Z05-0274 | 10/03/2006 | Granted | 10/03/2006 | V | Expenditure is a per annum amount |
2 | ARB | Z05-0274 | 12/09/2006 | Approved | 20/12/2006 | V | Agreement reached on compensation and access. |
3 | APV | Z05-0274 | 29/10/2007 | Approved | 04/09/2008 | V | Request for Minister's consent under Condition No. 2 |
5 | REN | Z05-0274 | 25/02/2008 | Approved | 02/10/2008 | V | Expenditure stated as a per annum amount. |
6 | EAO | Z05-0274 | 12/05/2009 | Approved | 13/05/2009 | V | SOIL SAMPLING PROGRAM - WARRADERRY STATE FOREST |
7 | REN | Z05-0274 | 09/03/2010 | Approved | 09/12/2010 | V | Expenditure is expressed as a per annum amount |
9 | REN | Z05-0274 | 22/02/2012 | Approved | 26/11/2012 | V | Expenditure is expressed as a per annum amount |
10 | EAA | MCV13/1116 | 20/12/2013 | Approved | 15/01/2014 | V | REF Proposed Percussion and Diamond Drilling Program |
11 | REN | Z12-3453 | 13/02/2014 | Approved | 08/04/2014 | V | Expenditure is expressed as a per annum amount |
12 | SRV | Z12-3453 | 14/02/2014 | Approved | 05/03/2014 | V | Increase Security |
13 | RSC | Z12-3435 | 29/05/2014 | Approved | 29/05/2014 | V | Top Up Cash security received |
14 | REN | V17-2157 | 10/03/2017 | Approved | 29/05/2017 | V | |
15 | CCR | V17-2157 | 08/04/2018 | Adequate | 07/08/2018 | V | 17/18 report received |
16 | CCR | V17-2157 | 16/04/2019 | Adequate | 16/04/2019 | V | 2019 CCR RECEIVED |
17 | REN | TMS-REN91 | 06/03/2020 | Approved | 08/06/2021 | V | |
18 | SRV | SF21/20245 | 17/02/2021 | Approved | 12/03/2021 | V | SRV increase Activity Approval |
19 | SRV | SF21/27084 | 10/03/2021 | Approved | 18/03/2021 | V | No Change SRV |
20 | RSC | SF21/20245 | 28/04/2021 | Approved | 28/04/2021 | V | RSC of SRV Security |
21 | SRV | SF21/83352 | 15/07/2021 | Approved | 12/08/2021 | V | SRV Decrease - RCE |
22 | DSC | SF21/83352 | 21/09/2021 | Approved | 21/09/2021 | V | Refund due to SRV reduction in security |
23 | RSC | SF21/83352 | 22/09/2021 | Approved | 22/09/2021 | V | RSC to receipt in security due to part refund |
24 | SRV | SF21/133124 | 18/10/2021 | Approved | 15/11/2021 | V | SRV Decrease to Secure Funding for Rehab Obligations |
26 | REN | REN-2023-88 | 07/03/2023 | Approved | 03/05/2023 | V | TMS |
29 | SRV | SEC0001717 | 02/05/2025 | Approved | 14/05/2025 | V | Security Condition Review - Variation to the assessed deposit amount determined |