1 | TTL | UNKNOWN | 03/02/1916 | Granted | 03/02/1916 | V | Title existed before computerisation |
5 | REN | T71-1937 | 01/01/1971 | Approved | 23/11/2001 | V | |
7 | TRF | C96-0336 | 25/07/1996 | Registered | 19/11/1996 | V | |
8 | RSC | C96-0336 | 09/10/1997 | Approved | 09/10/1997 | V | |
13 | SRV | C94-2325 | 18/09/2002 | Approved | 18/09/2002 | V | Southland colliery security see also general comments |
15 | ROY | T71-1937 | 23/11/2001 | Approved | 23/11/2001 | V | Royalty requirement added on renewal |
17 | RSC | C03-0543 | 21/09/2002 | Approved | 21/09/2002 | V | see general comments - Southland colliery security |
18 | RSC | C03-0543 | 31/01/2003 | Approved | 31/01/2003 | V | Southland MOP security |
19 | RSC | C03-0543 | 08/08/2003 | Approved | 08/08/2003 | V | Southland joint MOP sec |
20 | SRV | C03-0543 | 02/06/2004 | Approved | 02/06/2004 | V | Southland Colliery |
21 | AGR | Z04-4467 | 22/10/2004 | Registered | 09/11/2004 | V | Transfer of intersest from HSBC to Walter Turnbull P/L |
22 | TRF | Z04-4847 | 14/01/2005 | Registered | 05/04/2005 | V | Sale of Southland to Yanzhou Coal Company P/L |
23 | TRF | Z04-4847 | 28/04/2005 | Registered | 26/05/2005 | V | |
25 | SRV | Z03-0543 | 25/10/2005 | Approved | 25/10/2005 | V | Add MPL 204 to Single Security |
26 | DSC | C03-0543 | 04/11/2005 | Approved | 04/11/2005 | V | Relates to Dealing 30 |
27 | DSC | C03-0543 | 01/11/2005 | Approved | 01/11/2005 | V | Return of Individual Security following SRV |
28 | SRV | Z05-3190 | 25/06/2008 | Approved | 26/06/2008 | V | Increase in security following AEMR |
29 | RSC | Z05-3190 | 21/07/2008 | Approved | 21/07/2008 | V | Receipt of Security following AEMR |
30 | DSC | Z05-3190 | 22/07/2008 | Approved | 22/07/2008 | V | Replacement security received |
31 | RSC | Z05-3190 | 01/10/2009 | Approved | 01/10/2009 | V | Replacement security received |
32 | DSC | Z05-3190 | 01/10/2009 | Approved | 01/10/2009 | V | Release following receipt of replacement security |
33 | SRV | Z08-5269 | 18/03/2010 | Approved | 18/03/2010 | V | Delete MPL 324 from single security following cancellation |
34 | MSC | Z10-5918 | 04/09/2010 | Approved | 12/10/2010 | V | Letters of 27/8/10 re MAA changes were returned to sender. |
35 | SRV | Z08-5280 | 31/01/2011 | Approved | 31/01/2011 | V | Delete ML 1347 & PLL 150 from security after cancellation |
36 | SRV | T08-0157 | 22/11/2011 | Approved | 22/11/2011 | V | ML 1661 added to single security following Grant |
37 | SRV | Z09-2098 | 25/01/2012 | Approved | 25/01/2012 | V | Add ML 1666 to Single Security |
38 | RSC | Z05-3190 | 03/05/2012 | Approved | 03/05/2012 | V | Exchange of Security Certificate |
39 | DSC | Z05-3190 | 03/05/2012 | Approved | 03/05/2012 | V | Release original security certificate |
40 | SRV | Z09-2202 | 23/08/2012 | Approved | 23/08/2012 | V | Add ML 1677 (Act 1992) to single security |
41 | SRV | Z05-3190 | 26/02/2016 | Approved | 02/03/2016 | V | Increase security required |
42 | RSC | Z05-3190 | 19/04/2016 | Approved | 19/04/2016 | V | Increase security received |
43 | RSC | Z05-3190 | 11/10/2016 | Approved | 11/10/2016 | V | Received Security Certiificate |
44 | DSC | Z05-3190 | 11/10/2016 | Approved | 11/10/2016 | V | Exchanged Certificates |
45 | REN | V17-3139 | 12/04/2017 | Approved | 05/12/2017 | V | |
46 | APV | V12-5298 | 22/06/2018 | Approved | 22/06/2018 | V | Approve amendment to Mining Lease conditions 4 and 5 |
47 | SRV | Z05-3190 | 22/08/2019 | Approved | 20/09/2019 | V | Increase secuirty to $27,113,000 |
48 | RSC | SF19/86392 | 25/10/2019 | Approved | 25/10/2019 | V | Receipt security |
49 | RSC | SF19/118580 | 10/12/2019 | Approved | 10/12/2019 | V | New security certificate received to swap out old security. |
50 | DSC | SF19/118580 | 10/12/2019 | Approved | 10/12/2019 | V | Certificate exchanged with Yancoal representative directly |
51 | SRV | SF21/119115 | 23/09/2021 | Approved | 22/10/2021 | V | SRV decrease - RCE |
52 | RSC | MEG/SF21/119115 | 16/02/2022 | Approved | 20/02/2022 | V | RSC due to SRV Decrease - Provided Lower Value Certificate |
53 | DSC | MEG/SF21/119115 | 16/02/2022 | Approved | 16/02/2022 | V | DSC due to SRV Decrease |
54 | APV | VAU-2022-126 | 29/04/2022 | Approved | 31/08/2022 | V | Variation - Streamlining Mining Lease Conditions Project |
55 | SRV | RVF22/6666#58 | 23/06/2023 | Approved | 29/06/2023 | V | SRV to add ML1851 to group Security |
56 | SRV | MEG/08/7033#1 | 19/05/2024 | Approved | 20/06/2024 | V | SRV Increase to secure funding for rehab obligations |
57 | RSC | MEG/08/7033#1 | 11/07/2024 | Approved | 11/07/2024 | V | RSC for SRV Increase |
58 | SRV | SEC0001395 | 19/12/2024 | Approved | 19/12/2024 | V | Security Condition Review - Variation to the assessed deposit amount determined |
59 | RSC | TOM0000399 | 19/12/2024 | Approved | 19/12/2024 | V | Security Condition Review - Variation to the assessed deposit amount determined |
60 | DSC | TOM0000431 | 19/12/2024 | Approved | 19/12/2024 | V | Security Condition Review - Variation to the assessed deposit amount determined |