1 | DAP | Z04-0752 | 23/08/2004 | Granted | 23/08/2004 | V | |
2 | TRF | Z04-0752 | 11/10/2007 | Registered | 12/10/2007 | V | |
3 | PCN | Z04-0752 | 20/12/2007 | Approved | 20/12/2007 | V | Grant of New Titles ML 1605 & ML 1606 |
4 | SUS | Z04-0752 | 19/12/2007 | Approved | 26/12/2007 | V | Suspend and replace Special Condition 43 |
5 | TRF | Z08-0880 | 26/03/2008 | Registered | 31/03/2008 | V | Transfer to Moolarben, Sojitz and Kores |
6 | PCN | Z08-0880 | 24/02/2009 | Approved | 24/02/2009 | V | Part cancelled by the grant of ML 1628. |
7 | REN | Z08-0880 | 21/07/2009 | Approved | 02/12/2009 | V | |
8 | AGR | Z09-8218 | 02/12/2009 | Registered | 04/12/2009 | V | Moolarben Deed of Security |
10 | REN | Z12-4200 | 17/08/2012 | Approved | 12/05/2014 | V | |
11 | EAA | MCV13/477 | 22/08/2013 | Approved | 29/08/2013 | V | Exploration Activities SDN |
12 | EAA | MCV13/619 | 20/09/2013 | Approved | 01/11/2013 | V | Moolarben Coal Operations Underground 1 Exploration REF |
13 | PCN | Z12-4200 | 23/09/2013 | Approved | 23/09/2013 | V | PCN by Grant of ML 1691 |
14 | AGR | Z09-8218 | 09/10/2013 | Registered | 12/11/2013 | V | Yancoal General Security Deed dated 13 September 2013 |
15 | EAA | MCV13/685 | 10/10/2013 | Approved | 14/10/2013 | V | Ulan Seam Exploration Boreholes SDN Moolarben Coal Mines |
17 | SRV | Z12-4200 | 21/01/2014 | Approved | 21/01/2014 | V | Increase in security following submission of RCE |
18 | RSC | Z12-4200 | 25/03/2014 | Approved | 25/03/2014 | V | RCE - Underground 1 Exploration Project |
19 | DSC | Z12-4200 | 28/03/2014 | Approved | 28/03/2014 | V | Security updated |
20 | EAA | MCV14/709 | 23/05/2014 | Approved | 23/06/2014 | V | REF - Moolarben Exploration Drilling Program |
21 | SRV | Z12-4200 | 23/07/2014 | Approved | 31/07/2014 | V | Increase in security following submission of RCE |
23 | EAA | MCV14/606 | 17/04/2014 | Approved | 28/04/2014 | V | SDN - Moolarben's OC4 Prospect - Partially Cored HQ Holes |
25 | RSC | Z14-4200 | 07/10/2014 | Approved | 07/10/2014 | V | |
26 | DSC | Z12-4200 | 07/10/2014 | Approved | 07/10/2014 | V | Release of replaced security certificate no 202002800000024 |
27 | EAA | MCV15/301 | 10/04/2015 | Approved | 28/04/2015 | V | SDN - Moolarben Coal - UG1 North Area RIM Drilling Program |
28 | EAA | MCV15/375 | 13/05/2015 | Approved | 15/05/2015 | V | SDN - Moolarben Coal - Underground 4 (UG4) Drilling Program |
29 | EAA | MCV15/421 | 11/06/2015 | Approved | 16/06/2015 | V | SDN - Moolarben Coal Mine - Open Cut 4 Drilling Program |
30 | CCR | V12-4200 | 21/09/2015 | Adequate | 10/01/2018 | V | 14/15 Deemed adequate as part of Clearance Project |
31 | PCN | Z12-4200 | 31/08/2015 | Approved | 31/08/2015 | V | Part Cancelled by Grant of ML 1715 |
32 | PCN | Z15-2078 | 17/09/2015 | Approved | 03/01/2017 | V | Part Cancellation at Holders' Request |
35 | AGR | Z16-0222 | 18/02/2016 | Registered | 29/02/2016 | V | Deed of Release and Amendment |
36 | CCR | V12-4200 | 21/09/2016 | Adequate | 10/01/2018 | V | 15/16 - Deemed adequate as part of Clearance Project |
37 | RSC | Z12-4200 | 11/10/2016 | Approved | 11/10/2016 | V | Received Security Certificate |
38 | DSC | Z12-4200 | 11/10/2016 | Approved | 11/10/2016 | V | Security Certificate Exchanged |
39 | SRV | Z12-4200 | 05/06/2017 | Approved | 08/06/2017 | V | Increase in required security |
40 | RSC | Z12-4200 | 10/07/2017 | Approved | 10/07/2017 | V | Receipt of security certificate |
41 | CCR | Z12-4200 | 20/11/2017 | Adequate | 15/12/2017 | V | 16/17 Report received and assessed |
42 | REN | TMS-REN299 | 22/08/2017 | Approved | 11/12/2020 | V | V17-8926 |
43 | CCR | Z12-4200 | 21/09/2014 | Adequate | 22/09/2014 | V | CCR 13/14 - Technical Issue / Clearance Project |
44 | SRV | Z12-4200 | 06/01/2018 | Approved | 13/02/2018 | V | Increase in required security |
45 | RSC | Z12-4200 | 24/04/2018 | Approved | 24/04/2018 | V | |
46 | DSC | Z12-4200 | 24/04/2018 | Approved | 24/04/2018 | V | |
47 | SRV | Z12-4200 | 21/06/2018 | Approved | 09/08/2018 | V | Increase in Security Held |
48 | RSC | Z12-4200 | 14/09/2018 | Approved | 14/09/2018 | V | Receipt additional security for security review |
51 | SRV | Z12-4200 | 06/03/2019 | Approved | 24/04/2019 | V | |
52 | RSC | Z12-4200 | 30/05/2019 | Approved | 30/05/2019 | V | Receipt new certificate re SRV |
53 | CCR | 12/4200#1/DOI | 20/09/2019 | Adequate | 26/11/2019 | V | |
54 | PCN | V17-8926 | 26/02/2020 | Approved | 26/02/2020 | V | By Grant of MLA507 |
55 | TRF | TMS-TRF52 | 28/01/2021 | Registered | 24/02/2021 | V | TMS TRF52 |
56 | AGR | TMS-AGR15 | 29/05/2020 | Registered | 07/04/2021 | V | Moolarben Deed of Cross Charge dated 31 March 2020 |
57 | SRV | SF20/99319 | 15/10/2020 | Approved | 05/11/2020 | V | SRV increase |
58 | RSC | SF20/99319 | 23/11/2020 | Approved | 23/11/2020 | V | RSC of SRV security increase |
59 | SRV | SF21/10399 | 01/02/2021 | Approved | 01/03/2021 | V | SRV Increase Activity Approval |
60 | RSC | SF21/10399 | 15/03/2021 | Approved | 15/03/2021 | V | RSC OF SRV INREASE SECURITY |
61 | DSC | SF21/10399 | 09/03/2021 | Approved | 09/03/2021 | V | DSC of SRV security relating to decrease |
62 | DSC | SF21/10399 | 15/03/2021 | Approved | 15/03/2021 | V | DSC due to SRC swap |
63 | AGR | TMS-AGR11 | 22/05/2020 | Registered | 07/04/2021 | V | Amendment to Deed of Release & Cross Charge D52 |
64 | AGR | TMS-AGR11 | 22/05/2020 | Registered | 07/04/2021 | V | Amendment to Dealing 31 AGR Deed of Ack & Release |
65 | AGR | TMS-AGR11 | 22/05/2020 | Registered | 07/04/2021 | V | Amend Deed of Cross Charge D53 |
66 | RSC | MEG/EF21/14462#6 | 13/04/2022 | Approved | 13/04/2022 | V | RSC due to Swap |
67 | DSC | MEG/EF21/14462#6 | 26/04/2022 | Approved | 26/04/2022 | V | DSC to complete Swap |
68 | RSC | MEG/EF21/14462#22 | 22/02/2023 | Approved | 22/02/2023 | V | RSC due to security swap |
69 | DSC | MEG/EF21/14462#22 | 22/02/2023 | Approved | 22/02/2023 | V | DSC to complete security swap |
70 | RSC | MEG/EF21/14462#22 | 24/04/2023 | Approved | 24/04/2023 | V | RSC due to Certificate Swap |
71 | DSC | MEG/EF21/14462#22 | 24/04/2023 | Approved | 24/04/2023 | V | DSC to Complete Swap |
72 | SRV | MEG/08/880#1 | 05/07/2023 | Approved | 01/08/2023 | V | SRV Increase to Secure Funding for Rehab Obligations |
73 | REN | REN-2023-210 | 15/08/2023 | Approved | 05/12/2023 | V | TMS |
74 | RSC | MEG/08/880#1 | 22/08/2023 | Approved | 22/08/2023 | V | RSC due to SRV Increase |
75 | RSC | MEG/08/880#1 | 28/08/2023 | Approved | 28/08/2023 | V | RSC due to SRV Increase |
76 | SRV | SEC0001163 | 06/01/2025 | Approved | 06/01/2025 | V | Security Condition Review - Variation to the assessed deposit amount determined |
77 | RSC | TOM0000486 | 06/01/2025 | Approved | 06/01/2025 | V | Security Condition Review - Variation to the assessed deposit amount determined |
78 | RSC | TOM0000487 | 06/01/2025 | Approved | 06/01/2025 | V | Security Condition Review - Variation to the assessed deposit amount determined |